(WASHINGTON) Tomorrow, the United States Secret Service (USSS) and National Park
Service (NPS) will begin implementing a series of new, temporary security enhancements and
aesthetic improvements for the White House complex. These temporary measures are meant to
satisfy security needs while a long-term solution is designed and implemented.
Work will begin with E Street NW, followed by the Ellipse, and finish with the White House
complex fence. Work on the fence is expected to begin in early July. Both agencies will make
every effort to minimize construction impacts to visitors.
After the Oklahoma City bombing and the Sept. 11, 2001 attacks, the USSS implemented
closures and increased security measures around the White House, including closing E Street,
NW and the Ellipse to public vehicle access. Many of these security features used a combination
of concrete Jersey barriers, planters, and fencing.
The new, temporary security measures to E Street, NW and the Ellipse provide enhanced
protection for the White House, while improving the aesthetics at checkpoints. The temporary
design solution for the White House complex fence is meant to improve security, while
minimizing visual impacts and respecting the significance of the White House.
On May 8, work will begin on vehicle checkpoints on E Street, NW, starting at 17th Street
followed, by 15th Street, and then at the Ellipse. Crews will rearrange existing officer booths on
E Street, install a new officer booth at the Constitution Avenue entrance to the Ellipse, and
update the vehicle checkpoints by replacing concrete barriers with mobile steel plate barriers
which can be raised and lowered. These improvements are expected to be complete in early July.
A removable anti-climb feature consisting of sharp metal points will be installed on the top of the
White House fence. The feature is meant to deter and inhibit individuals who may attempt to
climb over the fence. Work is expected to begin in early July and take about four weeks. This
temporary measure will be in place until a long-term solution is implemented.
Concurrently, the USSS and NPS are working with other federal agencies to develop a long-term
design solution for the White House complex perimeter fence. Agencies have begun to review
preliminary design concepts and will select a final design later this summer. The final design will
be submitted to the Commission of Fine Arts (CFA) and National Capital Planning Commission
(NCPC) in the fall of 2015 for review and approval. Construction is expected to begin in 2016.
The NPS and USSS are also moving forward with the Presidents Park South Environmental
Assessment (EA), which will address long-term security for the White House complex outside of
the fence. The EA is expected to be completed by early 2016. Construction for these long-term
measures should begin mid-2017.
Both the CFA, on April 16, and the NCPC, today, approved interim security enhancements
proposed jointly by the USSS and NPS. We are appreciative of the thoughtful review and
approval of the Commissions on these important security enhancements for the White House
complex.
Source: U.S. Secret Service